Bernhard Findeiss
Wednesday July 8th, 2009

Scrum vs. Kanban (2/2)

In my last article, I began a little comparison between Scrum and Kanban: What are the key similarities and differences between the two methods?

This time, I’d like to talk a little bit more about the distribution of boards to teams, and how to work on different products at the same time.

This blog post is based on the previous one. If you haven’t read it until now, I suggest doing so before going on with the rest of this article.

As mentioned in part 1, a Scrum Board always shows the state of the current sprint for a certain team. At the end of each sprint, a new “potentially shippable product increment” is created, the items on the board are “reset”, and the next sprint begins. As a consequence, requirements to be implemented by a Scrum team mustn’t be more than one sprint in length. Bigger chunks must be split into smaller ones until they fit.

In Kanban, this is handled differently. As sprints do not exist, items can be of arbitrary length. Also a result of lacking sprints, a Kanban board doesn’t undergo the same cycle as a Scrum board, and is not reset after each sprint. But there are some similarities, however: The rows contain the various requirements, and the columns represent the states of the workflow. Requirements are “done” as soon as all tasks associated with it have moved to the right-most workflow state.

<———————————>

This is not the only difference between the two panels: In Scrum, the table exactly the work of a team again. While it may all see the blackboard, but the team may also change. The team is cross-functional occupied. I.e. all the capabilities needed to the current sprint to a successful conclusion, are included in the team.

In KANBAN are here from the outset, no such limits. Cross-functional teams are optional. Even the restriction to a single team is not required. Instead, it refers to a Kanban board to a specific workflow. A workflow can, in principle, but also include several teams. A Kanban table may be purchased by several teams changed.

To say it is better to be able to imagine, the whole thing again here graphically:

A Scrum-table is always in possession of a single team
Figure 1: A Scrum-table is always in possession of a single team

Figure 1 shows a typical Scrum board. She is always in possession of a single team. All columns of the table will only be changed by this team.

Figure 2: A Kanban board of several teams can be managed simultaneously
Figure 2: A Kanban board of several teams can be managed simultaneously

Figure 2 shows a Kanban board. It is not only not in possession of a single team. Instead, it reflects a workflow again (in this case simply “Todo -> Processing -> Done). The individual steps of the workflow may be arbitrarily divided in teams.

In this example, here is example the column “Todo” by only one person managed (which could, for example a kind of project manager or his Product Owner). For the remaining columns, however, is another team responsible. In reality, the board would be from Figure 2, probably a bit expanded to really useful to be able to work. Links of column 2 “Todo” could be a column about “backlog” to introduce a kind of disordered wishlist without prioritization, as the pool for all future requirements serves. Should any of the requirements to be realized, it will be easy for “Todo” postponed.

Of course you can have the workflow to many other types of distributed teams. With a high number of items it might be useful to some, that two or more teams share a column. But the Scrum used in case (a team manages the entire table) is possible.

A Scrum-table is really nothing other than the special case of a Kanban board.

Behaves similarly to the case also with the estimate of items, or their lead on the table:

In Scrum, use the length of an iteration as a frame of reference. This means that the team appreciates all the new incoming requests and selects them exactly as many as it is in this iteration (sprint) can be implemented. If one adds the estimated values of all the requirements of a sprint, so you get the “total value” of a sprint (in Function Points). We call this number also “Velocity”. This value can then several sprints continued to write and compare. He serves the team as a clue in the sprint planning when it comes to requirements for the next sprint to select.

Figure 3: Calculation of the Velocity
Figure 3: Calculation of the Velocity

In KANBAN, however, this is a bit different. Since it is of no house of iterations, and also the new requirements Beschätzung is not absolutely necessary, there is no fixed reference frame, one to calculate the velocity would use. Instead, we need to manage differently here. Some teams such requirements are grouped into so-called “MMF” (Minimum Marketable Features). Then they measure the time it takes all the requirements to implement this group. On this basis, can then also service level agreements (SLAs) are working. “We provide a MMF always at max. 10 days would be an example of this.

Other teams break requirements (without explicitly beschätzen) in approximately equal-sized pieces and then measure the throughput. Based on a fixed (arbitrarily chosen) time can be once again a “Velocity” calculate ( “10 requests per month).

The possibilities are almost limitless. One can of course always a fixed frame of reference to introduce, with estimates and / or re-iterations of a Scrum-like method come. The best way is to try different looks, and then take the one that is for the current case, the most appropriate.

Together, the two methods, however, the same team several products simultaneously work for you. In Scrum, you often feel that this does not work (as a Product Backlog is always based on just one product). However, one could indeed be a team on several product backlog at the same time to work. The order of execution (in a row, alternating each sprint, at the same time, etc.) will be given jointly by the team reached with the Product Owner (s) specified.

With KANBAN, the whole thing much easier: A blackboard always belongs to a workflow, rather than a product. It is therefore readily possible to use several products at the same time using the same workflow to drive. For better distinction, one could still take different cards, or you carry more than one line (one line per product). But otherwise, no further changes to the process necessary.

Where at first the comparison between Kanban and Scrum. Here are the results again in a table briefly summarized:
Scrum Kanban
Iterations with a fixed duration. Iterations are purely optional. Fixed length is not mandatory, also control event possible.
3 rolls firmly planned (Product Owner, Scrum Master and Team). Initial no prescribed roles.
Team selects a set of requirements for a sprint, and undertakes to implement this. None of iterations, therefore, no solid commitments necessary. But there is the possibility to introduce SLAs.
Velocity (work done per sprint) as the primary parameters for planning and improvement. Throughput as the primary parameter.
Product Backlog is (descending) sorted by business value. Prioritization optional.
Entries must be in the Product Backlog in a max. a sprint feasible. Scrum tasks on the board are <= 1 day. Requirements may be arbitrarily large.
No changes to the requirements during a sprint possible. New requirements will be the earliest with the next sprint planning. New requirements can in principle be brought at any time (if a slot is free).
A Scrum-table after each sprint will be reset. A Kanban board is continuously updated.
A Sprint Backlog (and thus also a Scrum-table) is always exactly one team. A Kanban table can have any teams to be divided.
Cross-functional teams required (and also necessary, as a Sprint Backlog only by one team is being processed). Cross-functional teams optional. Even more (special) teams per workflow possible.

If you look at this table so committed, then you can see quite well how Scrum and Kanban actually related: Kanban and Scrum are not mutually exclusive. Quite the contrary: Since every rule in Scrum is a special case of a rule is Kanban, Scrum is really nothing more than a special case of Kanban.

Scrum is one of (probably infinitely) many ways to make Kanban …

BFI mehr »

Last Sunday, there was a picture of our Federal Chancellor, Frau Dr. Merkel, in the onboard newspaper of MeinSchiff. The corresponding article contained some of what Frau Merkel had written for the “Tagesspiegel am Sonntag” of July, 5th, 2009.

I had to read no further than the first sentence to start getting thoughtful:

she will stand up for “getting the federal expenses back to a sustainable path after the crisis”.
mehr »

Roland Dürre
Tuesday July 7th, 2009

Eating, Eating, Eating, Shopping, Shopping, Shopping!

My Norwegian trip is still making me thoughtful.brandeinsessen1 I will write a few articles in order to mentally close it down. Here comes the first.

On the ship, I was one of the very slim people, which is amazing for someone weighing 95 kilograms and all the time trying to get back to his one-time weight of 85.

I found the following data on eating and overweight in Brandeins (copy of Mai 2009, page 85 “Gegessen wird immer”).

Per centage of overweight females in Germany:
66 
Per centage of overweight males in Germany:
51 
Per centage of German women who think they are too fat: 59
Per centage of German men who think they are too fat: 75


I am among both the 51 and 75.

mehr »

Bernhard Findeiss
Tuesday June 30th, 2009

Scrum vs. Kanban (1/2)

The topic Kanban frequently came up during recent discussions. Often associated with the question “Do you still use Scrum, or have you already changed to Kanban?”.

That gave me the impression that many people think of Kanban as being the “successor” to Scrum. However, this statement is wrong! The contratry is true: Scrum and Kanban are both based on the same ideas. Even more: Scrum is one possible way of doing Kanban…

A detailed paper on this has recently been published by Henrik Kniberg ( see here). But don’t worry, you don’t have to read everything in detail. I’ll give you a brief summary:

If you try to categorize today’s project management methods, you can base your categorization e.g. on the number of rules and regulations these models contain, and the number of areas these models cover.

mehr »

Roland Dürre
Sunday June 28th, 2009

(Deutsch) Die Überwindung von Zeit und Raum!

How to Conquer Time and Space!
bild0537A short while ago, I took part in a discussion on “The Sense and Benefit of WEB Pages for Radio and Television Stations”.

Some of the people I met who still had their doubts were quite competent and famous. Another participant, who is almost all the time travelling around the globe for an American world trust, was quite happy:

“I can hear Bayern 3 all around the world!”

“Heute im Stadion” (“Today in the Stadium”, the Federal League Soccer reports, Saturday at 3 p.m.) is “live” all around the world. German soccer fans listen to the reports from the football stadiums of the federal league no matter where they are and what they do: while they eat breakfast, while they have their laundry washed, during lunch or dinner, or else on their night watch. No matter which continent they are currently living on.
I am currently on a ship near Norway. Even here, I could (if I so desired) listen to current reports of Bayern 2 (and in theory all other radio stations of this world).

The answer to the question if the web makes sense for radio stations is quite simple:

Information starts surpassing the borders of space and time!

To me, that sounds quite sensational. Regardless of place, you can listen to any station you wish to, provided they offer their program on the internet! For quite some time, internet radio stations functioning through WLAN have successfully done their job just like normal radios. Using them, you can receive an “endless” number of radio stations.

And even if a program has been recorded in the past, I can still listen to it as podcast. Whenever and wherever I so desire. That is a little like the stars shining down on us from a long time ago.
When we still had nothing but short, medium, long and ultra-short waves, that was unconceivable. In those days, we recorded programs on our cassettes and later labelled them. How many fruitless attempts we made! How often did malfunctioning cassettes and tapes drive us crazy? Again a jumble of twisted tape! Or else, we got angry because the cassette recorder did, after all, not automatically start recording at the time we had programmed it to.

I once tried to get a few old programs from my past. No way! Even the big German television stations had nothing left in their archives.
Today, everything gets recorded for eternity. The archives of today will provide an excellent portrait of our times to later generations. And everything is centralized and can be loaded at any time! I wonder what influence this will have on historical research.

Personally, I prefer current programs. For me, the element of surprise and the feeling that I am hearing people in a live-program talking into the airwaves are important.

This is also why I am the only person in our family who does not own an MP3 player. As a compensation, I carry a normal, small ultra short wave receiver almost all the time. I am very selective about using it. Constant background music is my idea of hell.
So far, I have not downloaded a single podcast. Whenever I feel I would like to do so, I change my mind quite fast. After all, I know beforehand that there will, again, never be time to listen to it.

🙂 And besides, I prefer being a hunter to being a collector.

Well, and if ever I will change my mind or have more time, then this, too, is not a problem. After all, everything is centrally available at all times and places.

RMD
(translated by EG) mehr »

Sorry, this entry is only available in Deutsch.

Sorry, this entry is only available in Deutsch.

bundestagDuring the last years of his life (in the late 1960ies), the German psychologist and philosopher Karl Jaspers – who then became a Swiss citizen – concerned himself with the future of the Federal Republic of Germany.

In his last two books, he writes that the German democracy might well turn into a party oligarchy. This scenario gave him pause. I read a very interesting article of February 1983 by Rolf Hochhuth on this in the Zeit.

mehr »

Chris Wood
Wednesday June 3rd, 2009

Open Source Hardware

Recently, I have started to get material from an alumni society:
Cambridge_Computer_Lab_Ring.
See Cambridge_University_Computer_Laboratory.
In 1949, EDSAC, the first programmable electronic computer in the world ran there.
When I was one of its 17 students in 1964-65, it was still called “Mathematics Laboratory”.
A sort of Technology Park (silicon fen) has grown up near it.

In the wake of open source software, open source hardware is also becoming important. But, for no good reason, different intellectual property laws apply for it, so that the exact terms of open software licences cannot be applied. Jeremy Bennett wrote about the general situation in The Cambridge Computer Lab Ring. In the spirit of open source, he makes his article available to us. See www.embecosm.com/articles/ear1/open-source-hardware.pdf

I moved this article to the top because the third presentation is Monday, 8th of june!

darwin_flyer_sose09At Munich Technical University, there are always some interesting presentations that I like to hear. Now I got a special hint.
The Carl von Linde-Akademie at Munich Technical University organizes a lecture series on the revolution of the image of the world in nature, technology and society. Leading you through the presentation will be Prof. Dr. Klaus Mainzer (Academic Director of Carl von Linde-Akademie and chair holder in philosophy and scientific theory at TU München).

The same venue housed the presentation of Dr.-Ing. Wolfgang Reitzle, head of directors at Linde AG, on October, 21st, 2005 when he spoke about “Measuring in Terms of Humanity – What Makes Tomorrow’s Technologies a Success” at the series of the TUM Business Club. I also heard his special festive presentation when the Carl von Linde-Akademie was opened at May, 3rd, 2004 in the Pinakothek der Moderne on “The Culture of Responsibility and Innovation in Economy and Society”.

mehr »